Public contracts of Ydes · 2024 · Construction and buildings

Rénovation énergétique centre socio-culturel

Électricité

€53k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 7 October 2024 · ended around May 2025 · 7 months

Company selected

Électricité C TazeTravaux d'installation électrique dans tous locaux · registered office Bort Les Orgues (19110) · headcount 10 to 19 employees · SIREN 349912873

Number 5 by amount of the 7 contracts Ydes published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Rénovation énergétique centre socio-culturel: up to €53k over 7 months, Ydes 2024 · Qipu