Public contracts of Yutz · 2020
Extension du Dojo "Schuman"
Number 2 by amount of the 16 contracts Yutz awarded in 2020.
Contract · Construction and Bâtiment · carried out in 57970
250k €
contract ceiling — what was paid on it is not published
Who won it
Eiffage Construction Lorraine (Eiffage Construction Metz)SIREN 311962443The competition
Number of bids not published for that year: the field is only systematic from 2024.
Adapted procedure · awarded to 1 company
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
The form of the contract
PriceFerme et actualisable
Published amendmentsnone
The 2 lots
Lot 127 April 2020126k€
Lot 227 April 2020124k€
Other contracts of Eiffage Construction Lorraine (Eiffage Construction Metz) in Yutz
Requalification partielle des vestiaires du stade Mermoz202037k€Extension du Dojo "Schuman"201998k€Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.