San Francisco agreed $260,000 with SSI INC for contract 1000007260 (AIR Airport Commission); $7,150 has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.
Signed by Airport Commission
Sole-source
Agreed
$260,000
Paid
$7,150
3% of agreed
Remaining (calculated)
$252,850
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $3,750
Payment detail begins FY2018 ⓘ
The deal
Contract term
October 1, 2013September 30, 2018
Term ended
Recorded purchasing authority
Purchasing authority, verbatim
AIRPORT COMMISSION AUTHORITY - SOLE SOURCESole-source is a lawful procurement path that requires a waiver or commission approval. The wording above is the register’s, unedited. See every contract awarded under Sole-source waivers →