40201-MCK-CM AS Need-C

MCK AMERICAS INC · REC Recreation & Park Commsn

San Francisco agreed $973,225 with MCK AMERICAS INC for contract 1000015926 (REC Recreation & Park Commsn); $214,926 has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Register title:REC-40201-MCK-CM AS NEED-C

Signed by Recreation & Park Commsn

Agreed
$973,225
Paid
$214,926
22% of agreed
Remaining (calculated)
$758,299
The money
Paid against the agreed amount
Payments per fiscal year
2021222324252627
Largest year: $366,465 · dashed = fiscal year not closed yet

These bars total $658,302; the figure above is $214,926. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.

Payment detail begins FY2018
The deal
Contract term
September 13, 2019January 9, 2028
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICES

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
MCK AMERICAS INCPrime
PMA CONSULTANTS LLCSubcontractor$237,500
KITCHELLSubcontractor$125,000
C M PROSSubcontractor$112,500
A G S INCLBESubcontractor$87,500
INSPECTION SERVICES, INC./ STRUCTUS A JVSubcontractor$87,500
BIOLOGICAL MONITORING & ASSESS SPCLSTSSubcontractor$37,500
Architectural Testing, Inc.Subcontractor$26,775
+ 1 more on the team
A E W ENGINEERING INCLBESubcontractor$12,500

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.

Sources
This contract in the source
Raw rows (JSON, data.sfgov.org)