AIR50289 Noise Insul PRGR Cons
CSDA DESIGN GROUP · AIR Airport Commission
San Francisco agreed $8.8M with CSDA DESIGN GROUP for contract 1000024558 (AIR Airport Commission); $5.9M has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.
Register title: “AIR50289 NOISE INSUL PRGR CONS”
Signed by Airport Commission
These bars total $7.2M; the figure above is $5.9M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
| Supplier | Role | Attached $ |
|---|---|---|
| CSDA DESIGN GROUP | Prime | — |
| HILL INTERNATIONAL INC | Subcontractor | $600,000 |
| ENVIROSUITE CORP. | Subcontractor | $150,000 |
| TERRACON CONSULTANTS INC | Subcontractor | $150,000 |
| HARRIS MILLER MILLER & HANSON INC | Subcontractor | $75,000 |
| Pragmatic Professional Engineers | Subcontractor | $60,000 |
| THE JONES PAYNE GROUP INC | Subcontractor | $60,000 |
| ArchIT Inc. | Subcontractor | $30,000 |
+ 2 more on the team
| Edelman | Subcontractor | $30,000 |
| SINGER ASSOCIATES INC | Subcontractor | $30,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.