Airport construction: B-Smart Water

GALLIERA INC DBA TRICO CONSTRUCTION · AIR Airport Commission

The Airport Commission is paying a supplier for this under project 11076.61. The subject comes from the register's own abbreviated label. San Francisco agreed $2.4M with GALLIERA INC DBA TRICO CONSTRUCTION for contract 1000034868 (AIR Airport Commission); $426,660 has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

In plain English

The Airport Commission is paying a supplier for this under project 11076.61. The subject comes from the register's own abbreviated label.

Register title:AIR-11076.61-DBB-Smart Water

Signed by Airport Commission

LBE
Agreed
$2.4M
Paid
$426,660
18% of agreed
Remaining (calculated)
$1.9M
The money
Paid against the agreed amount
Payments per fiscal year
252627
Largest year: $1.4M · dashed = fiscal year not closed yet

These bars total $2.8M; the figure above is $426,660. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.

Payment detail begins FY2018
The deal
Contract term
January 27, 2025September 23, 2026
Term running
Recorded purchasing authority
Purchasing authority, verbatim
AIRPORT COMMISSION AUTHORITY - DOCUMENT BID

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
GALLIERA INC DBA TRICO CONSTRUCTIONLBEPrime
CRITCHFIELD MECHANICAL, INC.Subcontractor$491,435
Big Pipe MechanicalLBESubcontractor$264,619
JOHN BERTOLDI INCLBESubcontractor$129,600

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.