Original title: “PUC 8'&16' DIWM REPLC & INSTAL”
$1.9M
paid on this contract in FY2026
February 26, 2025December 17, 2026
Paid to
Cratus Incprime contractor$3.0MPaid from, FY2026
The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.
Water fund · multi-year projects$1.9M
Type and award
Contract type: Construction marked “unilateral”
Award: Competitive bid
The project team
Cratus IncPrime ContractorRonan Construction, Inc.Subcontractor · LBE$607,360
RK Engineering IncSubcontractor · LBE$485,440
Total Traffic Control, Inc.Subcontractor · LBE$250,000
Devaney Engineering, Inc.Subcontractor · LBE$200,000
Crana TruckingSubcontractor · LBE$100,000
DR Traffic ControlSubcontractor$0
Mike O'Dell SurveysSubcontractor$0
Contract 1000035464 · Source: Supplier Contracts · every payment on this contract