Contractor for Stanley Park Power Distribution Upgrade
In 2015, the City of Vancouver awarded “Contractor for Stanley Park Power Distribution Upgrade” (invitation to tender PS20150780) to Bay Hill Contracting for $1.3M. 3 vendors responded; offers ranged from $1.3M to $2.5M. Source: City of Vancouver open data, Awarded contracts, data as of 23 July 2026.
$1.3M
awarded on August 24, 2015
The competition
Bids on this competition3bids
Invitation to tender, 2015: median bids31 competitions · 2 with a single bid3bidsThe offers
The awarded offer was the lowest of the 3 priced offers.
Bay Hill ContractingAwarded$1.3MFred Thompson Contractors (1991)Not awarded$1.8MWestern Pacific Enterprises GPNot awarded$2.5MAbout these figures
Every response the City published for this competition, awarded first, then by price.
Awarded amounts are what the City agreed at award. What it later paid each supplier is published only in the annual Statement of Financial Information.