Skip to main content

Public contracts of Cherbourg-en-Cotentin · 2022 · Construction and buildings

Réhabilitation et extension du cosec complexe sportif de la saillanderie a la glacerie

€626k
maximum contract amount over 2.5 years — what was paid on it is not published
Signed on 11 May 2022 · ended around September 2024 · 2.5 yrs

That is at most ~€268k a year on average: a maximum too.

Company selected

Leduc SASTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Virandeville (50690) · headcount 50 to 99 employees · SIREN 312454515

The competition

1 bid received

Median for this procedure in 2022: 3 bids, across 2475 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 18 by amount of the 138 contracts Cherbourg-en-Cotentin published for 2022. It belongs to the policy Culture, sport and youth.

Other contracts of Leduc SAS in Cherbourg-en-Cotentin

Démolition reconstruction des vestiaires et tribunes au stade jean…2025 · maximum over 13 months125€kConstruction club house RCCH2024 · maximum over 14 months250€kTravaux d’aménagement et mise en conformité thermique accessibilité du…2023 · maximum over 2 years1.3€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : 13

Subcontracting declared : yes

The 3 lots : 480 €k · 93 €k · 53 €k

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.