Skip to main content

Public contracts of the Ain département · 2025

Rénovation énergétique du collège du Renon a vonnas 9 lots lot n 2 maçonnerie

€188k
maximum contract amount over 17 months — what was paid on it is not published
Signed on 3 November 2025 · running until about April 2027 · 17 months
Ongoing4 Apr 2027

That is at most ~€133k a year on average: a maximum too.

Company selected

Alpes Bourgogne Construction (Abc)Travaux de maçonnerie générale et gros œuvre de bâtiment · registered office Macon (71000) · headcount 10 to 19 employees · SIREN 493899116

The competition

36 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 112 by amount of the 246 contracts the Ain département published for 2025.

Other contracts of Alpes Bourgogne Construction (Abc) in Ain

Rénovation énergétique du collège du Renon à Vonnas2025 · maximum over 16 months179€kAmélioration de la ventilation au collège de Brou à Bourg en Bresse2025 · maximum over 4 months28€kTravaux d’installation de 2 élévateurs pour accessibilité PMR au…2021 · maximum over 3 months35€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 7

Subcontracting declared : yes

Social considerations : Clause sociale

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.