Public contracts of the Allier département · 2019

AXE Allier

Études techniques et dossiers réglementaires

€656k
maximum contract amount over 8 years — what was paid on it is not published
Signed on 8 July 2019 · running until about July 2027 · 8 yrs
Ongoing8 Jul 2027

That is at most ~€82k a year on average: a maximum too.

Company selected

Ingerop Conseil et Ingénierie (ICI)Ingénierie, études techniques · registered office Rueil Malmaison (92500) · headcount 1,000 to 1,999 employees · SIREN 489626135

A contract awarded to 2 holders; above, the main holder. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 5 by amount of the 110 contracts the Allier département published for 2019.

Other contracts of Ingerop Conseil et Ingénierie (ICI) in Allier

Maîtrise d’oeuvre pour la Construction du pont Via Allier RD 2009 à…2024 · maximum over 2 years49€kMission MO réfection générale du pont de Jenzat RD422022 · maximum over 3 years251€kMO pour la réfection de 3 buses métalliques2021 · maximum over 2.5 years76€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.