Skip to main content

Public contracts of the Allier département · 2023

Recyclage au liant hydrocarboné de la RD120 à Saint Nicolas des Biefs

€178k
maximum contract amount over 3 months — what was paid on it is not published
Signed on 9 May 2023 · ended around August 2023 · 3 months

Who won it

Eurovia Drome Ardeche Loire AuvergneConstruction de routes et autoroutes · registered office Saint-Jean-Bonnefonds (42650) · headcount 500 to 999 employees · SIREN 317975910

Number 33 by amount of the 92 contracts the Allier département published for 2023.

Other contracts of Eurovia Drome Ardeche Loire Auvergne in Allier

Aménagement et extension du centre de secours situé à Etroussat2026 · maximum over 7 months87€kRecyclage de la couche de roulement au liant hydrocarboné…2024 · maximum over 3 months771€kAccord cadre travaux avec mise en oeuvre d’enrobés années…2023 · maximum over 4 years8€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.