Skip to main content

Public contracts of Alsace · 2023

Structure bois métal dans le cadre de la construction du collège Katia et Maurice KRAFFT et construction d’une demi-pension

€2.3M
maximum contract amount over 3 years — what was paid on it is not published
Signed on 9 February 2023 · ended around April 2026 · 3 yrs

That is at most ~€727k a year on average: a maximum too.

Who won it

Girold Constructions BoisTravaux de charpente · registered office Barr (67140) · headcount 50 to 99 employees · SIREN 509625752

The competition

3 bids received

Median for this procedure in 2023: 3 bids, across 158 comparable contracts. Procedure with negotiation · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 8 by amount of the 414 contracts Alsace published for 2023.

Other contracts of Girold Constructions Bois in Alsace

Travaux de réfection de la cour et construction de préaux au collège…2026 · maximum over 6 months177€kRemplacement de la toiture amiantée des logements de fonction du…2026 · maximum over 6 months66€kTravaux d’aménagement du Bastion de l’Etoile…2025 · maximum over 3.5 years945€k
Contract details (procedure, price, amendments, lots)

Procedure : Procédure avec négociation

Price : Forfaitaire

Published amendments : 1

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.