Public contracts of the Aveyron département · 2020
Rénovation de la chaufferie Sarrus à Rodez
Remplacement de la chaudière gaz-3 lots
That is at most ~€240k a year on average: a maximum too.
Who won it
Ferreira ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Druelle Balsac (12510) · headcount 10 to 19 employees · SIREN 340248921A contract awarded to 3 holders; above, the main holder. With it: Thermatic. The amount is the whole contract’s: the DECP does not publish each holder’s share.
Number 27 by amount of the 117 contracts the Aveyron département published for 2020.
Contract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Révisable
Published amendments : none
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.