Skip to main content

Public contracts of the Cantal département · 2021

Construction d’un pôle routier a saint Flour

Gros oeuvre

€1.8M
maximum contract amount over 2.5 years — what was paid on it is not published
Signed on 29 November 2021 · ended around May 2024 · 2.5 yrs

That is at most ~€702k a year on average: a maximum too.

Who won it

Entreprise de Rosso PierreSIREN 394703904

A contract awarded to a consortium of 2 holders; above, the main holder. With it: Entreprise Roux. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 3 by amount of the 275 contracts the Cantal département published for 2021.

Other contracts of Entreprise de Rosso Pierre in Cantal

Remplacement de la passerelle skieurs sur la RD67-démolition gros oeuvre2021 · maximum over 6 months289€kConstruction hangar allanche2021 · maximum over 5 months193€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Mixte

Published amendments : 26

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.