Skip to main content

Public contracts of the Charente département · 2020

Travaux de construction du pôle logistique et administratif au Centre Départemental de l’Enfance Leclerc Chauvin à Angouleme

Gros-oeuvre

€138k
maximum contract amount over 11 months — what was paid on it is not published
Signed on 14 April 2020 · ended around March 2021 · 11 months

Who won it

BT-Go ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Fleac (16730) · headcount 20 to 49 employees · SIREN 509257192

Number 37 by amount of the 190 contracts the Charente département published for 2020.

Other contracts of BT-Go Construction in Charente

Restructuration du Centre Départemental de l’Enfance Leclerc-Chauvin à…2019 · maximum over 2 years337€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.