Public contracts of the Côtes-d'Armor département · 2022

Reconstruction partielle d’un bâtiment enseignement et restructuration de la Segpa et bâtiments annexes au collège Roger Vercel de Dinan

Charpente bois

€666k
maximum contract amount over 4 years — what was paid on it is not published
Signed on 9 June 2022 · ended around June 2026 · 4 yrs

That is at most ~€166k a year on average: a maximum too.

Company selected

BelliardTravaux de charpente · registered office Gorron (53120) · SIREN 433998358

The competition

2 bids received

awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 11 by amount of the 139 contracts the Côtes-d'Armor département published for 2022.

Other contracts of Belliard in Côtes-d'Armor

Reconstruction partielle d’un bâtiment enseignement…2022 · maximum over 4 years726€k
Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.