Public contracts of the Dordogne département · 2019

Construction d’un Gymnase au collège Leroi

Gourhan au Bugue

€65k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 3 May 2019 · ended around August 2020 · 15 months

That is at most ~€52k a year on average: a maximum too.

Who won it

Jacques Sudrie et FilsTravaux de plâtrerie · registered office Le Bugue (24260) · headcount 20 to 49 employees · SIREN 321522831

Number 36 by amount of the 53 contracts the Dordogne département published for 2019.

Other contracts of Jacques Sudrie et Fils in Dordogne

Création et réhabilitation des vestiaires au collège la Roche Beaulieu…2021 · maximum over 4 months9€kRéaménagement et agrandissement des bâtiments de la base de loisirs de…2020 · maximum over 22 months222€kAménagement du centre d’interprétation de la grotte de Cussac au…2020 · maximum over 3 months12€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.