Public contracts of the Drôme département · 2020

Travaux de mise en accessibilité des ERP du Département de la Drôme

Phase 1-Zone Nord

€122k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 28 May 2020 · ended around September 2020 · 4 months

Company selected

Adm Metal (Atout Fer)Travaux de menuiserie métallique et serrurerie · registered office Chabeuil (26120) · headcount 6 to 9 employees · SIREN 818975096

Number 66 by amount of the 171 contracts the Drôme département published for 2020.

Other contracts of Adm Metal (Atout Fer) in Drôme

Travaux de Grosses Réparations 2020-Déplacements2022 · maximum over 4 months69€kCTD de DIE · Construction du nouveau centre-26150 DIE des lots…2021 · maximum over 13 months44€kTravaux de Grosses Réparations 2020-Drôme Nord2020 · maximum over 3 months44€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.