Public contracts of the Gard département · 2024

Maîtrise d’oeuvre partielle, déconstruction et reconstruction du pont des Châtaigniers à Chamborigaud et création d’un ouvrage provisoire

€98k
maximum contract amount over 19 months — what was paid on it is not published
Signed on 10 April 2024 · ended around November 2025 · 19 months

That is at most ~€62k a year on average: a maximum too.

Company selected

Ingerop Conseil et Ingénierie (ICI)Ingénierie, études techniques · registered office Rueil Malmaison (92500) · headcount 1,000 to 1,999 employees · SIREN 489626135

The competition

1 bid received

Median for this procedure in 2024: 1 bid, across 3199 comparable contracts. Contract awarded without prior advertising or competitive bidding · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 72 by amount of the 148 contracts the Gard département published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Marché passé sans publicité ni mise en concurrence préalable

Price : Unitaire

Published amendments : 2

Subcontracting declared : no