Skip to main content

Public contracts of the Gironde département · 2019

Construction du Centre d’Exploitation Départemental de Cestas chemin de Marticot

€218k
contract ceiling — what was paid on it is not published
Signed on 8 August 2019 · ended around September 2020 · 13 months

Who won it

Conception-Realisation-MetallerieFabrication de portes et fenêtres en métal · registered office Canejan (33610) · headcount 6 to 9 employees · SIREN 819554452

Number 83 by amount of the 255 contracts the Gironde département published for 2019.

Other contracts of Conception-Realisation-Metallerie in Gironde

Menuiserie aluminium202199€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.