Public contracts of the Gironde département · 2019

Réfection des sanitaires de la cour au collège Henri Brisson à Talence

€74k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 2 July 2019 · ended around September 2019 · 2 months

Company selected

Ste Auxiliaire de ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Sainte-Bazeille (47180) · headcount 3 to 5 employees · SIREN 400981726

Number 141 by amount of the 268 contracts the Gironde département published for 2019.

Other contracts of Ste Auxiliaire de Construction in Gironde

Extension du préau, réaménagements intérieurs…2020 · maximum over 3 months195€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.