Public contracts of the Haute-Garonne département · 2022

Construction d’un collège 600 à Castelnau d’ESTRETEFONDS/

Photovoltaïque

€245k
maximum contract amount over 19 months — what was paid on it is not published
Signed on 25 November 2022 · ended around June 2024 · 19 months

That is at most ~€155k a year on average: a maximum too.

Company selected

Autan SolaireTravaux d'installation d'équipements thermiques et de climatisation · registered office Castanet-Tolosan (31320) · headcount 20 to 49 employees · SIREN 489270322

Number 81 by amount of the 188 contracts the Haute-Garonne département published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.