Public contracts of the Haute-Saône département · 2019
Travaux d’améliorations ponctuelles sur le réseau routier départemental
Programme 2019-2022
That is at most ~€1.3M a year on average: a maximum too.
Company selected
Eurovia Bourgogne Franche - ComteConstruction de routes et autoroutes · registered office Gevrey-Chambertin (21220) · headcount 500 to 999 employees · SIREN 348899295A contract awarded to 2 holders; above, the main holder. With it: Entreprise Roger Martin. The amount is the whole contract’s: the DECP does not publish each holder’s share.
Number 3 by amount of the 127 contracts the Haute-Saône département published for 2019.
Other contracts of Eurovia Bourgogne Franche - Comte in Haute-Saône
Fourniture, fabrication, transport et mise en oeuvre de grave-émulsion…2024 · maximum over 3.5 years8€MDES-NORD (UT de Vesoul et Lure2023 · maximum over 4 years10€MVoirie et réseaux divers2021 · maximum over 18 months233€kContract details (procedure, price, amendments, lots)
Procedure : Appel d'offres ouvert
Framework agreement : yes: orders follow, the amount is a ceiling
Price : Révisable
Published amendments : none
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.