Skip to main content

Public contracts of the Hautes-Alpes département · 2020

Études préliminaires sécurisation et suppression des passages a niveau / sécurisation carrefour ac RD 21

€50k
maximum contract amount over 5 months — what was paid on it is not published
Signed on 31 August 2020 · ended around January 2021 · 5 months

Company selected

Lombardi IngenierieIngénierie, études techniques · registered office Lyon (69003) · headcount 50 to 99 employees · SIREN 791606460

Number 75 by amount of the 78 contracts the Hautes-Alpes département published for 2020.

Other contracts of Lombardi Ingenierie in Hautes-Alpes

Reconstruction du pont neuf-missions de maîtrise d’oeuvre+etude…2023 · maximum over 6 months139€kReconstruction du pont neuf-missions de maîtrise d’oeuvre+etude…2022 · maximum over 15 months324€kTunnel des ardoisieres2021 · maximum over 3 years148€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.