Skip to main content

Public contracts of the Isère département · 2020

Construction aménag ext MDD gresivaudan barraux

€507k
maximum contract amount over 20 months — what was paid on it is not published
Signed on 16 September 2020 · ended around May 2022 · 20 months

That is at most ~€304k a year on average: a maximum too.

Company selected

Pierre StreiffTravaux d'installation d'équipements thermiques et de climatisation · registered office Saint-Martin-Le-Vinoux (38950) · headcount 50 to 99 employees · SIREN 341519056

Number 74 by amount of the 314 contracts the Isère département published for 2020.

Other contracts of Pierre Streiff in Isère

Construction des réserves muséographiques de Saint Martin d’Hères2026 · maximum over 2 years13.5€MConstruction du nouveau collège Lucie Aubrac à Grenoble2020 · maximum over 19 months1.3€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : 5

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.