Skip to main content

Public contracts of the Isère département · 2026

Maîtrise d’oeuvre restructuration collège condorcet construction salle de sport

€1.3M
contract ceiling — what was paid on it is not published
Signed on 16 January 2026 · running until about January 2030 · 4 yrs
Ongoing16 Jan 2030

Who won it

Sinequanon'Ingénierie, études techniques · registered office Echirolles (38130) · headcount 10 to 19 employees · SIREN 067500298

Main holder, with the largest amount. The contract has 10 holders; the others are not shown here yet.

The competition

4 bids received

Median for this procedure in 2026: 3 bids, across 584 comparable contracts. Procedure with negotiation · awarded to 10 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 60 by amount of the 419 contracts the Isère département published for 2026.

Other contracts of Sinequanon' in Isère

Maîtrise d’oeuvre pour la restructuration et la rénovation du centre…2026330€kMissions d’ordonnancement, pilotage et coordination…202656€kMaîtrise d’oeuvre restructuration collège Les Buclos Meylan2025645€k
Contract details (procedure, price, amendments, lots)

Procedure : Procédure avec négociation

Price : Mixte

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.