Skip to main content

Public contracts of the Jura département · 2025

Collège poligny

Rénovation thermique des bâtiments · Maçonnerie

€69k
maximum contract amount over 23 months — what was paid on it is not published
Signed on 31 December 2025 · running until about December 2027 · 23 months
Ongoing1 Dec 2027

That is at most ~€36k a year on average: a maximum too.

Company selected

Petigny ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Saint-Vit (25410) · headcount 10 to 19 employees · SIREN 520820457

Number 64 by amount of the 83 contracts the Jura département published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.