Skip to main content

Public contracts of the Landes département · 2021

Maîtrise d’oeuvre pour la reconstruction de l’administration accueil et construction du magasin sur le site des jardins de noneres a mont de marsan

€97k
maximum contract amount over 3 years — what was paid on it is not published
Signed on 4 March 2021 · ended around March 2024 · 3 yrs

That is at most ~€32k a year on average: a maximum too.

Who won it

Larbre IngenierieIngénierie, études techniques · registered office Gueret (23000) · headcount 20 to 49 employees · SIREN 487626731

A contract awarded to 5 holders; above, the main holder. With it: SLK Architectes, Idc, Ading, Bets B&M. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 88 by amount of the 133 contracts the Landes département published for 2021.

Other contracts of Larbre Ingenierie in Landes

Maîtrise d’oeuvre pour l’aménagement des plateaux r+1 2 3 et 4…2025 · maximum over 22 months64€kMaîtrise d'œuvre pour l’amélioration du confort thermique du bâtiment…2023 · maximum over 3.5 years61€kMaîtrise d’oeuvre pour la reconstruction de 2 gites…2022 · maximum over 3 years95€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.