Public contracts of the Lot département · 2019
Maîtrise d’oeuvre pour les travaux de restauration et de conservation au musée Jean-Lurçat à St-Laurent-les-Tours
That is at most ~€19k a year on average: a maximum too.
Who won it
Sthoa ArchitectureActivités d'architecture · registered office Montauban (82000) · headcount 6 to 9 employees · SIREN 511127490Number 60 by amount of the 110 contracts the Lot département published for 2019.
Contract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Révisable
Published amendments : none
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.