Skip to main content

Public contracts of Métropole de Lyon · 2024

Couzon au Mont d’Or

Maîtrise d’oeuvre pour la rénovation et l’élargissement du pont de Couzon / Rochetaillée sur la Saône

€350k
maximum contract amount over 3.5 years — what was paid on it is not published
Signed on 27 June 2024 · running until about February 2028 · 3.5 yrs
Ongoing26 Feb 2028

That is at most ~€95k a year on average: a maximum too.

Company selected

QuadricIngénierie, études techniques · registered office Neyron (01700) · headcount 20 to 49 employees · SIREN 338500713

A contract awarded to a consortium of 3 holders; above, the main holder. With it: Atelier de la Grande Cote (Anne Sophie Robin Architecte du Patrimoine), Strates Ouvrages d'Art et Architecture. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

12 bids received

Median for this procedure in 2024: 3 bids, across 17585 comparable contracts. Open tender · awarded to 3 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 114 by amount of the 259 contracts Métropole de Lyon published for 2024.

Other contracts of Quadric in Métropole de Lyon

Lyon 2-Centre d’échanges de Lyon Perrache2026 · maximum over 12 months3.4€M
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Mixte

Published amendments : none

Subcontracting declared : yes

Social considerations : Clause sociale

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.