Public contracts of Métropole de Lyon · 2019

Maîtrise d’oeuvre pour la réalisation de travaux de rénovation et d’extension de la station relais d’eau potable des Ardelets

Commune de Saint-Didier-au-Mont-D’or

€92k
maximum contract amount over 4 years — what was paid on it is not published
Signed on 12 June 2019 · ended around March 2023 · 4 yrs

That is at most ~€24k a year on average: a maximum too.

Who won it

Cabinet Montmasson - Ingenieurs ConseilsIngénierie, études techniques · registered office Annecy (74000) · headcount 10 to 19 employees · SIREN 391142403

Number 103 by amount of the 128 contracts Métropole de Lyon published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.