Skip to main content

Public contracts of the Moselle département · 2026

Exécution de l’opération d’aménagement foncier des communes de berling-hangviller

€248k
maximum contract amount over 4 years — what was paid on it is not published
Signed on 30 July 2026 · running until about September 2030 · 4 yrs
Ongoing29 Sept 2030

That is at most ~€60k a year on average: a maximum too.

Who won it

Cabinet Lambert et AssociesSIREN 494318702

The competition

3 bids received

Median for this procedure in 2026: 3 bids, across 8946 comparable contracts. Open tender · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 19 by amount of the 49 contracts the Moselle département published for 2026.

Other contracts of Cabinet Lambert et Associes in Moselle

Exécution de l’opération d’aménagement foncier de la commune de…2025 · maximum over 4 years252€kGéomètre à exécuter pour l’étude d’opérations intéressant la…2019 · maximum over 12 months37€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale