Public contracts of the Puy-de-Dôme département · 2025

RD8 Travaux aménagement traverse Tallende

€219k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 12 March 2025 · ended around July 2025 · 4 months

Who won it

Eurovia Drome Ardeche Loire Auvergne (Renon)Construction de routes et autoroutes · registered office Saint-Jean-Bonnefonds (42650) · headcount 500 to 999 employees · SIREN 317975910

Number 60 by amount of the 147 contracts the Puy-de-Dôme département published for 2025.

Other contracts of Eurovia Drome Ardeche Loire Auvergne (Renon) in Puy-de-Dôme

Travaux d’aménagement en traverse d’agglomération Effiat2026 · maximum over 8 months697€kTravaux aménagement en traverse d’agglomération effiat2026 · maximum over 6 months345€kRD18 et RD92-aménagt traverse servant2025 · maximum over 2 years149€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.