Public contracts of the Seine-Maritime département · 2024

Concours de maîtrise d’oeuvre pour la reconstruction partielle du collège Jean Zay à Sotteville-lès-Rouen

€1.4M
maximum contract amount over 6 years — what was paid on it is not published
Signed on 7 October 2024 · running until about October 2030 · 6 yrs
Ongoing8 Oct 2030

That is at most ~€226k a year on average: a maximum too.

Who won it

Acau ArchitectesActivités d'architecture · registered office Rouen (76000) · headcount 10 to 19 employees · SIREN 344382312

The competition

3 bids received

Median for this procedure in 2024: 2 bids, across 322 comparable contracts. Restricted tender · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 11 by amount of the 240 contracts the Seine-Maritime département published for 2024.

Other contracts of Acau Architectes in Seine-Maritime

Maîtrise d’oeuvre pour des travaux d’extension du centre d’exploitation…2025 · maximum over 18 months163€kConcours de maîtrise d’oeuvre pour la construction d’une demi-pension…2023 · maximum over 5 years551€kConcours de Maîtrise d’OEuvre pour la construction d’une demi-pension…2019 · maximum over 4 years371€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres restreint

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.