Skip to main content

Public contracts of the Somme département · 2023

Travaux de construction d’un préau au collège Jules Ferry à Conty

Gros Oeuvre / Charpente métallique / Couverture

€157k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 5 May 2023 · ended around September 2023 · 4 months

Who won it

Construction Metalliques BosquelloisesTravaux de montage de structures métalliques · registered office Poix-De-Picardie (80290) · headcount 20 to 49 employees · SIREN 395160369

The competition

2 bids received

Median for this procedure in 2023: 3 bids, across 8300 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 32 by amount of the 199 contracts the Somme département published for 2023.

Other contracts of Construction Metalliques Bosquelloises in Somme

Travaux de construction du CIS de Conty2026 · maximum over 12 months59€kTravaux de construction du CIS de Conty2026 · maximum over 12 months28€kTravaux de rénovation et d’extension de la demi-pension du collège…2025 · maximum over 7 months41€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.