Public contracts of the Somme département · 2022

Travaux de réaménagement du garage départemental à Abbeville

Gros-OEuvre

€208k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 10 February 2022 · ended around October 2022 · 8 months

Company selected

Lhotellier Construction (JPL GC)Construction d'autres bâtiments · registered office Blangy-Sur-Bresle (76340) · headcount 100 to 199 employees · SIREN 504177759

The competition

36 bids received

awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 35 by amount of the 193 contracts the Somme département published for 2022.

Other contracts of Lhotellier Construction (JPL GC) in Somme

Travaux de construction de la Bibliothèque départementale de la Somme…2026 · maximum over 18 months945€kTravaux d’aménagement de l’ex-atelier en salle pour séminaires2023 · maximum over 7 months141€kTravaux de mesures de sécurisation et de mesures d’urgences du logis du…2022 · maximum over 3 months183€k
Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.