Skip to main content

Public contracts of the Somme département · 2024

Travaux de rénovation énergétique du collège Jean Moulin à Moreuil

Menuiseries extérieures · Métallerie

€1.8M
maximum contract amount over 16 months — what was paid on it is not published
Signed on 19 December 2024 · ended around April 2026 · 16 months

That is at most ~€1.4M a year on average: a maximum too.

Company selected

LoisonTravaux de menuiserie métallique et serrurerie · registered office Armentieres (59280) · headcount 100 to 199 employees · SIREN 320291164

The competition

4 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 10 by amount of the 134 contracts the Somme département published for 2024.

Other contracts of Loison in Somme

Travaux de construction de la Bibliothèque départementale de la Somme…2026 · maximum over 18 months102€kRemplacement de menuiseries extérieures dans 9 collèges du Département…2025 · maximum over 6 months43€kTravaux de mise en accessibilité du collège Béranger à Péronne2023 · maximum over 4 months63€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Subcontracting declared : yes

Social considerations : Clause sociale

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.