Public contracts of the Yonne département · 2020

Maîtrise d’œuvre de mise aux normes accessibilité pour collèges ne nécessitant pas d’ascenseur ou élévateur (Joigny, Paul Fourrey, Jacques Prevert, Paron…

€216k
maximum contract amount over 4 years — what was paid on it is not published
Signed on 29 December 2020 · ended around December 2024 · 4 yrs

That is at most ~€54k a year on average: a maximum too.

Who won it

Team ConceptActivités d'architecture · registered office Torcy (77200) · headcount 6 to 9 employees · SIREN 511765018

The competition

2 bids received

awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 22 by amount of the 101 contracts the Yonne département published for 2020.

Other contracts of Team Concept in Yonne

Maîtrise d’œuvre pour la rénovation énergétique du bâtiment A par pose…2021 · maximum over 4 years108€k
Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.