Skip to main content

Public contracts of Ézanville · 2022 · Construction and buildings

Travaux de menuiserie pour des façades du groupe scolaire Village

€12k
maximum contract amount over 3 months — what was paid on it is not published
Signed on 20 June 2022 · ended around September 2022 · 3 months

Company selected

R.G.BTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Saint-Ouen-L'Aumone (95310) · headcount 3 to 5 employees · SIREN 794660910

Number 12 by amount of the 13 contracts Ézanville published for 2022. It belongs to the policy Schools.

Other contracts of R.G.B in Ézanville

Travaux de remplacement de faux plafonds2022 · maximum over 3 months30€kMaçonnerie2021 · maximum over 3 months117€kPlomberie2021 · maximum over 3 months12€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.