Public contracts of Bordeaux Métropole · 2024

Travaux de Mise en état correct du groupe scolaire Maurice Ravel à Talence/

Électricité courants forts et faibles

€150k
maximum contract amount over 2.5 years — what was paid on it is not published
Signed on 8 July 2024 · running until about October 2026 · 2.5 yrs
Ongoing8 Oct 2026

That is at most ~€66k a year on average: a maximum too.

Company selected

Sefco EntreprisesTravaux d'installation électrique dans tous locaux · registered office Pessac (33600) · headcount 10 to 19 employees · SIREN 499868933

The competition

4 bids received

Median for this procedure in 2024: 3 bids, across 17585 comparable contracts. Open tender · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 242 by amount of the 481 contracts Bordeaux Métropole published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.