Skip to main content

Public contracts of Communauté d'agglomération Alès Agglomération · 2025

Pose de comptages pour la sectorisation du réseau d’eau potable sur plusieurs communes d’Alès Agglomération

€270k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 1 September 2025 · ended around September 2026 · 12 months

Company selected

Entreprise Rene Benoi et FilsConstruction de réseaux pour fluides · registered office Boisset-Et-Gaujac (30140) · headcount 20 to 49 employees · SIREN 314198250

A contract awarded to a consortium of 6 holders; above, the main holder. With it: Cevenole Aménagement Infras Construction, SOC Exploitation Ets Bonnefille, Epuration Pompage Urbain et Rural, Canonge et Biallez, Julia SI3e. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

2 bids received

Median for this procedure in 2025: 3 bids, across 49612 comparable contracts. Simplified procedure · awarded to 6 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 28 by amount of the 67 contracts Communauté d'agglomération Alès Agglomération published for 2025.

Other contracts of Entreprise Rene Benoi et Fils in Communauté d'agglomération Alès Agglomération

Travaux de renouvellement des conduites structurantes de refoulement…2025 · maximum over 10 months3.6€MConstruction de la nouvelle station d’épuration de boisset et gaujac2025 · maximum over 19 months2.2€MBrignon2024 · maximum over 4 months122€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.