Public contracts of Communauté d'agglomération Bourges Plus · 2026
TEGR bâtiments
Électricité
That is at most ~€85k a year on average: a maximum too.
Company selected
Construction Électrotechnique du BAT (Cebat 2)Travaux d'installation électrique dans tous locaux · registered office Bourges (18000) · headcount 20 to 49 employees · SIREN 451235451A contract awarded to 2 holders; above, the main holder. With it: SE d'Électricité et de Chauffage. The amount is the whole contract’s: the DECP does not publish each holder’s share.
The competition
Median for this procedure in 2026: 3 bids, across 10562 comparable contracts. Open tender · awarded to 2 companies
Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.
Number 36 by amount of the 82 contracts Communauté d'agglomération Bourges Plus published for 2026.
Other contracts of Construction Électrotechnique du BAT (Cebat 2) in Communauté d'agglomération Bourges Plus
Reconstruction accueil aire des GENS du voyage des 4 vents2025 · maximum over 6 months147€kTravaux entretien et réparations des bâtiments2022 · maximum over 3 years150€kContract details (procedure, price, amendments, lots)
Procedure : Appel d'offres ouvert
Framework agreement : yes: orders follow, the amount is a ceiling
Price : Unitaire
Published amendments : none
Social considerations : Clause sociale
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.