Public contracts of Communauté d'agglomération Cannes Pays de Lérins · 2024

Travaux d’intervention d’urgence sur les infrastructures d’assainissement

Travaux de renouvellement/extension de réseaux · De réhabilitation et de travaux…

€1.5M
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 31 January 2024 · running until about January 2028 · 4 yrs
Ongoing31 Jan 2028

That is at most ~€375k a year on average: a maximum too.

Company selected

Rampa Travaux PublicsConstruction de réseaux pour fluides · registered office Le Pouzin (07250) · headcount 250 to 499 employees · SIREN 323468991

A contract awarded to 4 holders; above, the main holder. With it: Ac BTP, AD3G BTP, Entreprise Jean Brosio SA (Brosio TP). The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

4 bids received

Median for this procedure in 2024: 3 bids, across 17972 comparable contracts. Open tender · awarded to 4 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 16 by amount of the 130 contracts Communauté d'agglomération Cannes Pays de Lérins published for 2024.

Other contracts of Rampa Travaux Publics in Communauté d'agglomération Cannes Pays de Lérins

Travaux de pose de réseaux de thalassothermie et d’eau potable…2026 · maximum over 8 months1.2€MTravaux de pose de réseaux de thalassothermie et d’eau potable…2026 · maximum over 9 months625€kTravaux de restructuration du réseau d’eaux usées secteur ecureuils…2025 · maximum over 7 months1€M
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.