Public contracts of Communauté d'agglomération Cholet Agglomération · 2024

Travaux de conformité électrique de réparation et d’entretien des installations courant fort courant faible 2025-2028

€800k
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 16 December 2024 · running until about December 2028 · 4 yrs
Ongoing16 Dec 2028

That is at most ~€200k a year on average: a maximum too.

Company selected

Cegelec Loire OcéanTravaux d'installation électrique dans tous locaux · registered office Carquefou (44470) · headcount 250 to 499 employees · SIREN 537916165

The competition

2 bids received

Median for this procedure in 2024: 3 bids, across 48741 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Amounts paid

Electricity, gas and heating: €800k paid by Communauté d'agglomération Cholet Agglomération in 2024, all suppliers together (its accounts). The accounts do not say what share went to Cegelec Loire Océan.

Number 11 by amount of the 65 contracts Communauté d'agglomération Cholet Agglomération published for 2024.

Other contracts of Cegelec Loire Océan in Communauté d'agglomération Cholet Agglomération

Électricité2026 · maximum over 4 years1€MÉclairage général de la patinoire sportive2026 · maximum over 4 months96€kPanneaux photovotaiques et raccordement électrique2025 · maximum over 12 months602€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : 3

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.