Skip to main content

Public contracts of Communauté d'agglomération Concarneau Cornouaille Agglomération · 2026

Électricité

€41k
maximum contract amount over 2.5 years — what was paid on it is not published
Signed on 21 July 2026 · running until about January 2029 · 2.5 yrs
Ongoing19 Jan 2029

That is at most ~€16k a year on average: a maximum too.

Company selected

Ouest Électricité CornouailleTravaux d'installation électrique dans tous locaux · registered office Quimper (29000) · headcount 6 to 9 employees · SIREN 894770148

The competition

4 bids received

Median for this procedure in 2026: 3 bids, across 23502 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 64 by amount of the 83 contracts Communauté d'agglomération Concarneau Cornouaille Agglomération published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Social considerations : Critère social

Environmental considerations : Clause environnementale, Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.