Public contracts of Communauté d'agglomération Concarneau Cornouaille Agglomération · 2025

Maîtrise d’oeuvre pour le projet LowKAL / Construction du FabLab Konk Ar Lab

€97k
contract ceiling — what was paid on it is not published
Signed on 26 February 2025 · running until about February 2028 · 3 yrs
Ongoing27 Feb 2028

Who won it

Atelier MosSIREN 500593546

The competition

12 bids received

Median for this procedure in 2025: 3 bids, across 49224 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 67 by amount of the 132 contracts Communauté d'agglomération Concarneau Cornouaille Agglomération published for 2025.

Other contracts of Atelier Mos in Communauté d'agglomération Concarneau Cornouaille Agglomération

Maîtrise d’œuvre lowkal fablab202697€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Clause environnementale, Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.