Skip to main content
Bischwiller, in Communauté d'agglomération de Haguenau
Photo (Bischwiller): Didivo67, CC0

Grand Est · 100,343 residents · Chair: Claude Sturni

Communauté d'agglomération de Haguenau

€85.7 million spent in 2025.

€854 per resident · Urban-area groupings of the same size: €687

What Communauté d'agglomération de Haguenau spends, by policy

  • Administration and shared services24%€20.7M

    Bodies do not all file the same costs here: some put all their staff under it.

  • Education23%€19.9M
  • Streets and transport11%€9M
  • Town planning and housing9%€8.1M
  • Culture, sport and youth9%€7.3M
  • Loans: repayments and interest8%€6.9M
  • Public safety5%€4.3M
  • Waste, water and environment4%€3.5M
  • Health and social care4%€3.3M
  • Economy and trade3%€2.3M
The 2 other items (< 1%)
  • Passed on to other bodies< 1%€327k
  • Not assigned to a policy< 1%€86k

Source: 2025 accounts of Communauté d'agglomération de Haguenau (DGFiP), by public policy.

Suppliers and recipients

The same €85.7M, by recipient.

  • Staff50%€43.2M

    Pay and contributions.

  • Companies and contractors26%€22.5M

    See the names ↓

  • Banks and lenders8%€6.9M
  • Grants and contributions8%€6.8M
  • Compulsory contributions4%€3.1M
  • Joint bodies and syndicates< 1%€327k
  • Other3%€3M

    Councillors’ allowances, taxes paid, other costs.

Source: 2025 accounts of Communauté d'agglomération de Haguenau (DGFiP).

231 contracts signed in 2025 · €81.5M before tax

Why this total differs from the €22.5M paid to companies

These are the amounts of the contracts signed in the year, over their whole length, not what was paid. The money paid in a year also goes to older contracts and to purchases too small to be published (under €40,000 excl. VAT). For a framework agreement, the amount is a ceiling.

Investment and works

€10.5M of capital spending in 2025 (building, renovation, equipment), €105 per resident. Urban-area groupings of the same size: €114.

Click a building site to see the contract

Largest works contracted since 2023, among published contracts. Amounts planned at signature, often spread over several years.

On top of that, €63k paid to other bodies for their own equipment (towns, intercommunalities, associations…).

Source: 2025 accounts of Communauté d'agglomération de Haguenau (DGFiP), by public policy.

Revenue and financing

Revenue: €85.4M · borrowing: €6M · spending: €85.7M.

Breakdown of resources

  • Taxes (business and household taxes, VAT share)34%€30.7M
  • Users and rents33%€29.7M
  • State and other contributions16%€14.9M
  • Grants for works and VAT refunds8%€7.6M
  • Other receipts3%€2.5M
  • Borrowing7%€6M

Source: OFGL, 2025 accounts of the main budget.

Debt and taxes

€1,175 of debt per resident

Urban-area groupings of the same size: €781

13 years of savings to repay it

€31 of local taxes per resident

Urban-area groupings of the same size: €49

2025 accounts. Debt and taxes: OFGL, consolidated (main and side budgets). Per resident: amount divided by the population (Insee). “Urban-area groupings of the same size”: median of the 94 urban-area groupings of 100,000 to 365,000 residents.

The levels above Communauté d'agglomération de Haguenau

Spending per resident in 2025, and what each level pays for.

  • IntercommunalityCommunauté d'agglomération de HaguenauWaste, water, urban transport, economic development
    €854
  • RegionGrand EstHigh schools, regional trains, training, business support
    €662

Each row: the body’s own spending per resident, the figure at the top of its page (DGFiP). Not to be added up: a grant from one level is spent by another.

Who is part of Communauté d'agglomération de Haguenau

Understanding these figures

Who does what

The intercommunality collects and treats waste, often runs water and sanitation, organises urban transport, and pays part of its revenue back to its member towns.

Official table of responsibilities (July 2025)

Why the levels are not added up

The same euro can appear twice: once when a region or a département pays a grant, again when the town spends it. Each page shows its own body’s spending.

Where these figures come from

Spending: the accounts of the main budget published by the DGFiP, by public policy. Revenue, debt and taxes: OFGL. Contracts: published contract data (DECP), amounts planned at signing.

Do you work for Communauté d'agglomération de Haguenau, or sit on its council? A figure to correct, context to add: write to us.

Page edited by Qipu, independent of Communauté d'agglomération de Haguenau · Sources and method

Accounts 2025 (DGFiP, OFGL). The method · See the source