Maîtrise d’oeuvre relative à la réhabilitation de la station d’épuration de Lamure-sur-Azergues Le Charbonnier
That is at most ~€82k a year on average: a maximum too.
Company selected
Agence Architecture Brosselard et TroncyActivités d'architecture · registered office Vougy (42720) · headcount 3 to 5 employees · SIREN 381552181A contract awarded to a consortium of 2 holders; above, the main holder. With it: Realites Environnement. The amount is the whole contract’s: the DECP does not publish each holder’s share.
The competition
Median for this procedure in 2023: 3 bids, across 8300 comparable contracts. Simplified procedure · awarded to 2 companies
Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.
Number 15 by amount of the 46 contracts Communauté d'agglomération de l'Ouest Rhodanien published for 2023.
Other contracts of Agence Architecture Brosselard et Troncy in Communauté d'agglomération de l'Ouest Rhodanien
Maîtrise d’œuvre réhabilitation STEP lamure sur azergues2025 · maximum over 3.5 years67€kContract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Forfaitaire
Published amendments : 3
Subcontracting declared : no
Environmental considerations : Critère environnemental, Clause environnementale
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.