Travaux sur les réseaux d’eau potable de la Communauté d'agglomération de la Région Dieppoise

€4M
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 9 July 2026 · running until about July 2030 · 4 yrs
Ongoing9 Jul 2030

That is at most ~€1M a year on average: a maximum too.

Who won it

DRConstruction d'autres ouvrages de génie civil n.c.a. · registered office Saint-Saens (76680) · headcount 50 to 99 employees · SIREN 341024917

A contract awarded to 3 holders; above, the main holder. With it: Sogea Nord Ouest Travaux Publics, Sade - Compagnie Générale de Travaux Hydrauliques. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

6 bids received

Median for this procedure in 2026: 3 bids, across 20741 comparable contracts. Simplified procedure · awarded to 3 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

The largest of the 12 contracts Communauté d'agglomération de la Région Dieppoise published for 2026.

Other contracts of DR in Communauté d'agglomération de la Région Dieppoise

Travaux sur les réseaux d’assainissement de la Communauté…2025 · maximum over 4 years4€MTravaux sur les réseaux d’eau potable de dieppe maritime2021 · maximum over 4 years4€MTravaux sur les réseaux d’assainissement de dieppe-maritime2020 · maximum over 4 years4€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Mixte

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.